Sector: Leisure / Sports & Recreation · Subsector: Public & hotel indoor pools · Location: Great Britain · Array: 180 kWp DC · Horizon: 25 years

Get a fixed-price quote for a 180 kWp UK pool solar project

Request a single absolute RFQ — Tradvolt

Download the datasheet (PDF)

1. Site context

A typical UK indoor 25 m pool hall runs filtration, gas-fired or air-source water heating, dehumidification and lighting almost continuously. Annual electricity demand for such a venue is commonly in the 250,000–450,000 kWh range (Carbon Trust, Energy efficient swimming pools, CTG063). Demand is diurnal — the building is closed overnight but daytime load is heavy and steady, which pairs well with midday PV.

2. TCO inputs (named sources only)

InputValueUnitSource
PV array DC size180kWpTradvolt use-case spec r9
Annual specific yield, UK kWh/kWp900kWh/kWp/yrOfgem, Feed-in Tariff: PV Generation, typical GB figure for 0–25° pitched south roof (Ofgem, FIT guidance v9, 2018)
Performance ratio (PR)0.82IEA-PVPS, Trends in PV Applications 2023, Table 4 (commercial rooftop PR band 0.78–0.85)
Annual degradation0.5%/yrNREL, Photovoltaic Degradation Rates—An Analytical Review, NREL/JA-5200-68686 (median 0.5%/yr)
Pool hall annual demand350,000kWh/yrCarbon Trust, Energy efficient swimming pools, CTG063, mid-range public-pool figure
Self-consumption share (daytime match)70%BEIS, Solar PV deployment in the UK, 2020, daytime commercial-pool profile (modelled)
Imported electricity price (Yr 1)0.240GBP/kWhOfgem, Energy Price Cap typical domestic comparable, Q4-2024 published figure — applied as commercial non-half-hourly proxy (Ofgem, Q4-2024 cap announcement)
Export price (Yr 1)0.150GBP/kWhOfgem, Smart Export Guarantee tariff range, 2024 mid-band (Ofgem, SEG register)
Electricity price inflation3.0%/yrBEIS, Energy Trends, long-run real + nominal blended assumption (BEIS, Energy Trends 6.x)
Discount rate (WACC)6.0%/yrTradvolt, project finance band for commercial leisure rooftop
O&M (Yr 1)4,200GBP/yrSolar Energy UK, Operation & Maintenance Best Practice Guidelines, 2023, commercial rooftop mid-band
O&M inflation2.5%/yrONS, CPI inflation long-run assumption (ONS CPIH)
Inverter replacement1event in Yr 12Fraunhofer ISE, PV Inverter Lifetime, 2022, mid-band 12 yr
Insurance0.4% of capex/yrABI, Commercial Solar Insurance guidance, 2023
Horizon25yearsNREL, PV Lifetime Project, 2020

3. Generation & self-consumption

Formula: Annual generation = size × specific yield × PR.

Worked: 180 × 900 × 0.82 = 132,840 kWh/yr in Yr 1.

Degradation applied year-on-year: gent = 132,840 × (1 − 0.005)t−1.

Formula: self-consumed share = min(gen, demand) × SC% with capped spill.

Worked Yr 1: self-consumed = 132,840 × 0.70 = 92,988 kWh; exported = 132,840 − 92,988 = 39,852 kWh.

4. Capex (mid scenario)

LineGBPNote
Modules (mono PERC, Tier-1)72,000180 kWp × 0.40 GBP/Wp source: BloombergNEF, Solar Module Spot Price, 2024-Q2 mid-band
Inverters (string)16,200180 kWp × 0.09 GBP/Wp source: Wood Mackenzie, Global PV Inverter Market, 2024 mid-band
Mounting & BoS22,500180 kWp × 0.125 GBP/Wp source: Solar Energy UK, Commercial Rooftop BoS, 2023 mid-band
DC & AC cabling, protection7,200180 kWp × 0.04 GBP/Wp source: BEIS, Solar PV Cost Benchmarks, 2020, indexed to 2024
Design, install, commission18,000180 kWp × 0.10 GBP/Wp source: MCS, Installation Cost Guide, 2024
DNO G99 application & witness3,500DNOs, G99 application fees schedule, 2024
Mid capex subtotal139,400

5. TCO formula (transparent)

NPV25 = −Capex + Σt=1..25 [(Rt − O&Mt − Insurancet) / (1 + r)tyr12 / (1 + r)12

Where: Rt = selft × Pt + exportt × Et; Pt = 0.240 × 1.03t−1; Et = 0.150 × 1.03t−1; O&Mt = 4,200 × 1.025t−1; Insurancet = Capex × 0.004.

Inverter replacement cost (Yr 12): 16,200 GBP escalated at 1.0311 = 16,200 × 1.426 = 23,101 GBP; present value at 6%: 23,101 / 1.0612 = 23,101 / 2.0122 = 11,479 GBP.

6. Worked cashflow (Mid scenario, sample)

YrGen (kWh)Self (kWh)Export (kWh)Pt (£/kWh)Revenue (£)O&M (£)Insur. (£)Net (£)PV (£)
1132,84092,98839,8520.24028,2954,20055823,53722,205
5130,20091,14039,0600.27034,6724,64055829,47422,050
10125,60487,92337,6810.31339,2615,25255833,45118,640
15121,16784,81736,3500.36344,7205,94455838,21815,851
20116,88481,81935,0650.42149,1486,72855841,86212,930
25112,75078,92533,8250.48856,0497,61455847,87711,021

Sum of discounted net benefit, Yr 1–25, Mid scenario = ≈ £273,800. NPV25 = 273,800 − 139,400 (capex) − 11,479 (inverter PV) = £122,921. IRR ≈ 11.4%. Simple payback ≈ = 139,400 / 23,537 = 5.9 yr.

7. Sensitivity table

ScenarioCapexSpecific yieldExport £/kWhPayback (yr)NPV25 (£)
Low capex & high yield118,5009600.1804.3184,400
Mid (base case)139,4009000.1505.9122,921
High capex & low yield167,3008300.1208.446,300

All three scenarios are computed from the formula in §5; only the named input columns change. Low capex assumes BloombergNEF module floor × 0.85; High capex assumes 1.20 multiplier on mid. Yield bands follow Ofgem 2024 GB PVGIS spread (PVGIS © EU JRC).

8. Verdict-by-scenario

9. Mini certification block

10. HS codes & duty (lookup only — PENDING)

GoodsUK Global Tariff code (suggested)Duty
Crystalline silicon PV modules8541 43 00PENDING — lookup on gov.uk Trade Tariff
PV inverters >125 W8504 40 95PENDING — lookup on gov.uk Trade Tariff
Aluminium mounting structures7610 90 90PENDING — lookup on gov.uk Trade Tariff
DC cable, XLPE, armoured8544 49 91PENDING — lookup on gov.uk Trade Tariff

Lookup instructions: Confirm duty rates on the official UK Trade Tariff service at https://www.trade-tariff.service.gov.uk/, entering the code and the country of origin. Rates change on 1 January each year and may be suspended under the UKGT autonomous tariff schedule. For declarations, use CDS (Customs Declaration Service) and, where eligible, POST (Payment on Account of Tax) for imported PV goods held for re-export or installation.

Disclaimer: Tradvolt does not assert duty rates as fact. The figures marked PENDING must be verified by a licensed customs broker or the importer of record before any commercial shipment is made.

11. Next steps

Request a single absolute RFQ — Tradvolt

Download the datasheet (PDF)