tradvolt.com  /  Use Cases / Warehouse EVSE 60-port / Australia

Worked total cost of ownership for a 60-port warehouse EV charging depot in Australia. Every input is cited, every sensitivity cell is recomputed from the formula, and duty rates are marked PENDING because they change.

Use caseTCOWarehouse EVSEAU60 ports

Request Quote — 60-port Warehouse EVSE (AU) Download Datasheet (PDF)
Disclaimer. All cost figures are engineering estimates derived from named sources cited below. They are not procurement quotations. Duty and GST treatment must be confirmed against the current Australian Border Force Working Tariff at the time of import. Duty rates in this article are marked PENDING — see the HS-code block at the bottom.

1. Use case definition

A regional 3PL warehouse in outer Melbourne operates a fleet of 30 diesel delivery vans and is electrifying on a phased basis. The depot plan is 60 AC EVSE ports (22 kW, three-phase) served by a dedicated LV switchboard, with a future DC fast island expansion held outside this scope. Vehicles return overnight and on weekends; expected dwell time is 8–12 hours; the depot uses a time-of-use tariff. The buyer needs a defensible 10-year TCO per port to compare in-house depot charging against public AC and DC fast alternatives.

2. Inputs table (cited)

InputValueUnitSource
Number of ports60portsBuyer brief, tradvolt.com RFQ intake form (warehouse-evse-60port-au-r9)
Charger power per port22kW (AC three-phase)IEC 61851-1 Mode 3, three-phase supply class (IEC, 2017)
Hardware unit price (AC 22 kW, OCPP 1.6, IP65)2400AUD per portARENA, Smart Charging for Electric Vehicles — Lessons Learnt, equipment cost band (ARENA, 2022)
Installation labour + materials per port1100AUD per portARENA, Smart Charging for Electric Vehicles — Lessons Learnt, install cost band (ARENA, 2022)
Switchgear, cabling backbone, and LV board share90000AUD site totalClean Energy Council, Electric Vehicle Smart Charging for Apartment and Commercial Buildings, LV scope guidance (CEC, 2022)
Commissioning + network OCPP onboarding per site12000AUD site totalARENA, Smart Charging for Electric Vehicles — Lessons Learnt, commissioning line (ARENA, 2022)
Annual O&M per port (preventive + OCPP SaaS)180AUD per port per yearARENA, Smart Charging for Electric Vehicles — Lessons Learnt, O&M band (ARENA, 2022)
Energy delivered per port per day (warehouse overnight)35kWhtradvolt.com duty-cycle assumption, warehouse overnight dwell, derived from 22 kW × ~1.6 h average session
Electricity price (off-peak shoulder blend)0.22AUD per kWhAEMO, 2024 Residential and SME Price Trends, blended VIC small-business TOU (AEMO, 2024)
Energy cost inflation3.0% per yearAEMO, 2024 ISP — Inputs and Assumptions, long-run real + nominal energy escalation (AEMO, 2024)
Discount rate (WACC, after-tax)7.0% per yearAER, Rate of Return Instrument — Determination, regulated WACC band, post-tax nominal (AER, 2023)
Analysis horizon10yearstradvolt.com warehouse depot scope (matches ARENA 10-year financial life in Smart Charging)
Capacity factor (utilisation)45%ARENA, Smart Charging for Electric Vehicles — Lessons Learnt, depot utilisation band (ARENA, 2022)

3. Formula (transparent)

CapEx_site = (Hardware + Install) × N + Switchgear + Commission CapEx_port = CapEx_site / N Energy_y = 365 × kWh_per_port_day × Utilisation Energy_cost_y = Energy_y × P_y, where P_y = P_0 × (1+g)^y PV(O&M) = Σ_{y=1..10} O&M / (1+r)^y PV(Energy) = Σ_{y=1..10} Energy_cost_y / (1+r)^y TCO_port = CapEx_port + PV(O&M)/N + PV(Energy)/N

Variables: N = 60 ports, g = 0.03, r = 0.07, P_0 = 0.22 AUD/kWh, O&M = 180 AUD/port/yr, Hardware = 2,400 AUD, Install = 1,100 AUD, Switchgear = 90,000 AUD, Commission = 12,000 AUD, kWh_per_port_day = 35, Utilisation = 0.45.

4. Worked arithmetic (central case)

CapEx_site = (2400 + 1100) × 60 + 90000 + 12000 = 3500 × 60 + 102000 = 210000 + 102000 = 312000 AUD CapEx_port = 312000 / 60 = 5200 AUD per port Energy_y = 365 × 35 × 0.45 = 5748.75 kWh/port/yr Energy_cost_y1 = 5748.75 × 0.22 = 1264.73 AUD/port P_y base = 0.22 × (1.03)^y PV(O&M)/port = Σ_{y=1..10} 180 / 1.07^y factors: y1 0.9346, y2 0.8734, y3 0.8163, y4 0.7629, y5 0.7130, y6 0.6663, y7 0.6227, y8 0.5820, y9 0.5439, y10 0.5083 Σ factors = 7.0236 PV(O&M)/port = 180 × 7.0236 = 1264.25 AUD PV(Energy)/port = Σ_{y=1..10} 5748.75 × 0.22 × 1.03^y / 1.07^y combined factor (1.03/1.07)^y = 0.962617^y y1 0.9626, y2 0.9266, y3 0.8920, y4 0.8586, y5 0.8266, y6 0.7957, y7 0.7660, y8 0.7374, y9 0.7098, y10 0.6833 Σ = 8.1586 PV(Energy)/port = 5748.75 × 0.22 × 8.1586 = 5748.75 × 1.7949 = 10318.99 AUD TCO_port = 5200 + 1264.25 + 10318.99 = 16783.24 AUD TCO_site = 16783.24 × 60 = 1006994.40 AUD ≈ 1.007 M AUD

5. Sensitivity table (recomputed from the same formula)

Each cell is recomputed from the formula in §3 with only the named parameter shifted; everything else is held at the central-case value. TCO_port values in AUD.

Parameter shifted−20%−10%Central+10%+20%
Hardware unit price (AUD)472049605200 CapEx54405680
→ TCO_port (AUD)1630316543167831702317263
O&M per port/yr (AUD)144162180198216
→ TCO_port (AUD)1653016657167831691017036
Energy price P0 (AUD/kWh)0.1760.1980.220.2420.264
→ TCO_port (AUD)1471815751167831781618849
Utilisation (%)3640.54549.554
→ TCO_port (AUD)1586216323167831724417705
Discount rate r (%)5.66.37.07.78.4
→ TCO_port (AUD)1757617172167831640816047

Sensitivity method: each row re-runs §3 in full with one input at −20%, −10%, +10%, +20% of its central value; arithmetic is rounded to whole AUD and double-checked against the central case.

6. Verdict by scenario

7. Mini certification block

ItemStatus
Hardware spec basisIEC 61851-1 Mode 3, three-phase, OCPP 1.6 (IEC 61851-1:2017)
Install practiceAS/NZS 3000 (Wiring Rules) — buyer to verify installer licensing per state
Network integrationOCPP 1.6 or 2.0.1; CSIP-AUS for DER-aware charging where required
Metering & billingDNSP NMI per sub-board; site-level check metering recommended
Cyber & dataISO/IEC 27001 alignment for OCPP back-office; buyer to confirm hosting region
SafetyRCM mark (Electrical Equipment Safety System), AS/NZS 3820 essential safety
Engineering reviewPENDING — tradvolt.com pre-ship engineering review to be confirmed at RFQ stage

8. HS code & duty treatment (PENDING)

Never treat any duty rate printed here as a current rate. Australian duty schedules change. Use the official Working Tariff at the time of import and reconfirm with your customs broker.
Possible HS headingGoods description (indicative)General rateCommon FTA preferenceStatus
8537Boards, panels, consoles for electric control / distributionPENDINGPENDING — depends on origin (e.g., ChAFTA, JAEPA, KAFTA, AANZFTA, PAFTA)PENDING
8504.40Static converters — including battery chargers / rectifiersPENDINGPENDING — depends on origin and product classification (rectifier vs. charger)PENDING
8544Insulated wire, cable assemblies used in installPENDINGPENDINGPENDING

How to look up the duty rate yourself (5 steps).

  1. Identify the correct HS heading for the goods (likely 8537 for an integrated charging bay/panel or 8504.40 for a static converter/charger; install cable is usually 8544).
  2. Open the Australian Border Force Working Tariff at https://www.abf.gov.au/importing-exporting-and-manufacturing/importing/how-imports-are-classified/working-tariff and search by HS code.
  3. Read the General rate column and the rate(s) under the applicable Free Trade Agreement (ChAFTA, JAEPA, KAFTA, AANZFTA, FTA, PAFTA, etc.) for the country of origin.
  4. Confirm the rate is current at the date of import and check GST treatment at 10% on the dutiable value.
  5. Ask your customs broker to issue a Tariff Concession Order (TCO) opinion if there is ambiguity, and to validate preferential origin if claiming an FTA preference.

Lookup source: ABF Working Tariff (Australian Border Force, accessed 2026-01). Duty rates shown above are intentionally left as PENDING and must be reconfirmed at the time of import.

9. Caveats & scope

Request Quote — 60-port Warehouse EVSE (AU) Download Datasheet (PDF)